MARSHALL COUNTY – A contractor for the Kentucky Transportation Cabinet plans to begin a project to resurface around two miles of roadway in Marshall County in the Kenlake State Resort Park Golf Course area on Friday.
The project will resurface KY 80 from the Calloway-Marshall County line (0 mm) east to U.S. 68 (1.937 mm), approximately 1.937 miles of roadway.
The contractor will begin milling the roadway on Friday. Motorists should be alert for lane restrictions and flaggers that will last through the project.
Paving will begin on Monday and is scheduled to last from 7 to 10 days.
Motorists should be alert for one lane traffic with alternating flow controlled by flaggers. Some delays are possible during the movement and placement of equipment to facilitate the work.
Appropriate caution is required where equipment, flaggers, and maintenance personnel are along the roadway in close proximity to traffic flow.